(1) |
Where
within a per period of sixty days or in cases falling under clause (b) of section
236 within a period of thirty days, after the receipt of any notice under section
238 or section 239 or of the further information, if any, required under section
240, the Chairperson does not refuse to sanction the building or work or upon
refusal, does not communicate the refusal to the person who has given the notice,
the Chairperson shall communicate the refusal to the person who has given the
notice, the Chairperson shall be deemed to have accorded sanction to the building
or work and the person by whom the notice has been given shall be free to commence
and proceed with the building or work in accordance with his intention as expressed
in the notice and the documents and plans accompanying the same: Provided that
if it appears to the Chairperson that the site of the proposed building or work
is likely to be affected by any scheme of acquisition of land for any public purpose
or by any proposed regular line of a public street or extension, improvement,
widening or alteration of any street, the Chairperson may withhold sanction of
the building or work for such period not exceeding three months as he deems fit
and the period of sixty days or as the case may be, the period of thirty days
specified in this sub-sanction shall be deemed to commence from the date of the
expiry of the period for which the sanction has been withheld |
(3)
|
If the person or anyone lawfully claiming under him does not commence the erection
of the building or the execution of the work within one year of the date on which
the building or work is sanctioned or is deemed to have been sanctioned, he shall
have to give notice under section 238 or, as the case may be, under section 239
for fresh sanction of the building or the work and the provisions of this section
shall apply in relation to such notice as they apply 9n relation to the original
notice |
(4)
| Before
commencing the erection of a building or execution of a work within the period
specified in sub-section (3), the person concerned shall give notice to the Chairperson
of the proposed date of the commencement of the erection of the building or the
execution of the work Provided that if the commencement does not take place within
seven days of the date so notified, the notice shall be deemed not to have been
given and a fresh notice shall be necessary in this behalf. |