           (ii) provide real time data feeds which can be leveraged for a real time
                decisions and actions to strategize Demand Side management, Energy
                / Power Demand Forecasting.
          (iii) the data analytics can be leveraged for better peak load management
                and tariff structure planning.

           (iv) enhance consumer satisfaction level with  better  complaint
                management, faster  restoration  of outages and awareness  for
                optimized consumption pattern.
           (v) improve system stability, reliability and transparency.
           (vi) optimize O&M expenses.

        6.1.4  For improving power distribution infrastructure in NDMC area,
        following works have been completed in the year 2018-19:
            (i) NDMC received a grant of Rs. 32 crore from PFC under IPDS against
                the approved grant of Rs.119 crore.
           (ii) Energy Efficiency Services Ltd.  (EESL) provided 51000 single and
                three phase smart energy  meters  replacing the old static meters.
                Implementation of “Advance Metering Infrastructure” (AMI), which
                would help in improving NDMC’s revenue.

          (iii) Two  33/11 KV  electric sub  stations  have  been established in “East
                Kidwai Nagar” housing complex and made operational.
           (iv) For release of additional electric load to Safdarjung Hospital, a new
                33/11 KV power transformers and 33 KV GIS sub-stations has been
                commissioned.
           (v) Two 11  KV electric  sub-stations  for “National War Memorial”,  at
                India Gate established.
           (vi) An electric sub-stations for “Delhi Police Memorial”, in Chanakyapuri
                established and commissioned.

          (vii) Augmentation of HT/LT panels distributions transformers in various
                11 KV sub-stations at AIIMS, New Delhi completed.
         (viii) New electric connection and sub-station provided for Western Court
                Hostel at Janpath New Delhi.




        ----------------------------------------------------------------------------------------------------------------------------------