ELECTRIC CONNECTION : TECHNICAL FEASIBILITY FOR MAJOR LOADS

 

  • Submission of application along with all documents (0 days)
  • Field inspection (3 days)
  • Estimate preparation, loan sanction & Intimation for fee deposit (4 days)
  • Installation of meter and flow of electricity (8 days)